Community Participation Program Summary - Phase III

JUMP TO PHASE I REPORT --- JUMP TO PHASE II REPORT

EPIC
Citation
Strategy Name
CPP
Program
Income
NRP
Rollover
Total
Mod #s
Affecting
Strategy
COMMUNITY ENGAGEMENT
1.1.1 2011 Engagement Efforts $42,326.30     $42,326.30  
1.1.2 2012-13 Engagement Efforts          
1.1.3 2014-16 Engagement Efforts $142,000.00     $142,000.00  
TOTAL COMMUNITY ENGAGEMENT FUNDS$184,326.30     $184,326.30  
NEIGHBORHOOD PRIORITIES
2.1.1 Reserve $58,635.03     $58,635.03  
2.1.2 Community Connection/Public Safety/Crime Prevention $43,500.00     $43,500.00  
2.1.3 New Home Construction $120,000.00     $120,000.00  
COMMUNITY INNOVATION FUND
3.1.1 2015 CIF Native Youth Arts Collective $25,000.00     $25,000.00  
TOTAL NEIGHBORHOOD PRIORITY FUNDS$222,135.03     $222,135.03  
TOTAL ALLOCATIONS$431,461.33     $431,461.33  
EPIC Community Participation Program Summary (SU-7 P3) run on 11/21/2017 at 4:07 AM