Community Participation Program Status - Phase III

JUMP TO PHASE I REPORT --- JUMP TO PHASE II REPORT


EPIC
Strategy
Funds Approved
Funds Contracted
Funds
Available
to Contract
Citation
Name
CPP
NRP
Rollover
Community
Innovation
Fund
Program
Income
Total
Contract
Number
Funds
Under
Contract
Vendor
COMMUNITY ENGAGEMENT
1.1.1 2011 Engagement Efforts $42,326.30       $42,326.30
Total
28966
$42,326
$42,326
 
East Phillips Improvement Coalition
 
1.1.2 2012-13 Engagement Efforts           Total 
 
1.1.3 2014-16 Engagement Efforts $142,000.00       $142,000.00
Total
38872
$142,000
$142,000
 
East Phillips Improvement Coalition
 
NEIGHBORHOOD PRIORITIES
2.1.1 Reserve $58,635.03       $58,635.03 Total 
$58,635
2.1.2 Community Connection/Public Safety/Crime Prevention $43,500.00       $43,500.00
Total
39073
$8,000
$8,000
 
Easr Phillips Improvement Coalition
$35,500
2.1.3 New Home Construction $120,000.00       $120,000.00
Total
40699
40516
N/A
$60,600
$15,300
$15,300
$30,000
 
Powderhorn Residents Group
Powderhorn Residents Group (PRG)
PRG, Inc.
$59,400
COMMUNITY INNOVATION FUND
3.1.1 2015 CIF Native Youth Arts Collective     $25,000.00   $25,000.00
Total
40013
$25,000
$25,000
 
East Phillips Improvement Coalition (EPIC)
 
TOTAL$406,461.33   $25,000.00   $431,461.33   $277,926   $153,535

Neighborhood Priorities
Primary Public Contact
Status
Stage
2.1.2 Community Connection/Public Safety/Crime Prevention NCR Neighborhood Support : Carrie AspinwallNeighborhood Priority is undergoing ImplementationImplementation began 5/11/2015
3
2.1.3 New Home Construction CPED Housing Policy & Dev: Earl PettifordNeighborhood Priority is approvedImplementation began 8/3/2016
3
EPIC Community Participation Program Status (SU-10 P3) run on 09/26/2017 at 1:08 PM
N-Neighborhood is 68 EPIC
STAGES
1. Approved by the City for further development by the neighborhood and public staff
2. Assessment is underway by the neighborhood and public staff to determine course of action
3. Implementation has begun - a course of action has been determined and resources have been identified
4. Completed