Community Participation Program Status - Phase III

JUMP TO PHASE I REPORT --- JUMP TO PHASE II REPORT


Standish Ericsson
Strategy
Funds Approved
Funds Contracted
Funds
Rolled
to N2020
Citation
Name
CPP
NRP
Rollover
Community
Innovation
Fund
Program
Income
Total
Contract
Number
Funds
Under
Contract
Vendor
COMMUNITY ENGAGEMENT
1.1.1 2011 Engagement Efforts $87,436.05       $87,436.05
Total
28765
$87,436.05
$87,436.05
 
Standish Ericsson Neighborhood Association
 
1.1.2 2012-13 Engagement Efforts $105,101.65       $105,101.65
Total
35921
$105,101.65
$105,101.65
 
Standish Ericsson Neighborhood Association
 
1.1.3 2014-16 Engagement Efforts $236,299.35       $236,299.35
Total
37583
$236,299.35
$236,299.35
 
Standish Ericsson Neighborhood Association
 
1.4 2017-21 Engagement Efforts $378,768.00       $378,768.00
Total
41834
$378,768.00
$378,768.00
 
Standish Ericsson Neighborhood Association
 
NEIGHBORHOOD PRIORITIES
2.1.1 Reserve            
 
2.1.2 SUN Multi-Family Housing            
 
2.1.3 SUN Programmatic Equity at Parks            
 
2.1.4 SUN Property Inspections            
 
TOTAL$807,605.05       $807,605.05   $807,605.05    

Neighborhood Priorities
Primary Public Contact
Status
Stage
2.1.2 SUN Multi-Family Housing Neighborhood Priority is approvedApproved on 7/5/2014
1
2.1.3 SUN Programmatic Equity at Parks Neighborhood Priority is approvedApproved on 7/5/2014
1
2.1.4 SUN Property Inspections Neighborhood Priority is approvedApproved on 7/5/2014
1
Standish Ericsson Community Participation Program Status (SU-10 P3) run on 04/19/2024 at 10:30 PM
N-Neighborhood is 58 Standish Ericsson
STAGES
1. Approved by the City for further development by the neighborhood and public staff
2. Assessment is underway by the neighborhood and public staff to determine course of action
3. Implementation has begun - a course of action has been determined and resources have been identified
4. Completed